DELIVERY ROADMAP

Dynamic SDLC Planner

Explore the complete delivery lifecycle, phase timing, engineering allocation and sprint alignment for SprintIQ Platform.

Total phases 8 Lifecycle stages
Timeline 12 Weeks planned
Sprints 12 Delivery iterations
Capacity 2160 Effective hours
ACTIVE PROJECT

SprintIQ Platform

Agile Medium complexity 6 engineers
PHASE ROADMAP

Lifecycle intelligence

Every phase is generated from the current project configuration.

01 10.0% timeline

Discovery & Requirements

2026-07-05 2026-07-12
Duration 8 days
Engineers 3
Team load 50.0%
Core discovery and analysis team
Mapped sprints
S1 S2
02 10.0% timeline

Architecture & Planning

2026-07-13 2026-07-20
Duration 8 days
Engineers 3
Team load 50.0%
Focused senior technical capacity
Mapped sprints
S2 S3
03 10.0% timeline

UX/UI & Technical Design

2026-07-21 2026-07-28
Duration 8 days
Engineers 3
Team load 50.0%
Focused senior technical capacity
Mapped sprints
S3 S4
04 40.0% timeline

Development

2026-07-29 2026-08-31
Duration 34 days
Engineers 6
Team load 100.0%
Peak implementation capacity
Mapped sprints
S4 S5 S6 S7 S8 S9
05 15.0% timeline

Integration & QA

2026-09-01 2026-09-13
Duration 13 days
Engineers 4
Team load 66.67%
Validation and defect resolution
Mapped sprints
S9 S10 S11
06 7.0% timeline

UAT

2026-09-14 2026-09-19
Duration 6 days
Engineers 4
Team load 66.67%
Validation and defect resolution
Mapped sprints
S11
07 3.0% timeline

Deployment

2026-09-20 2026-09-22
Duration 3 days
Engineers 3
Team load 50.0%
Controlled release support
Mapped sprints
S12
08 5.0% timeline

Hypercare

2026-09-23 2026-09-26
Duration 4 days
Engineers 2
Team load 33.33%
Post-release stabilization
Mapped sprints
S12
SPRINT ALIGNMENT

Phase-to-sprint map

See how lifecycle phases cross each delivery iteration.

S1
Sprint 1 2026-07-05 → 2026-07-11
Discovery & Requirements
S2
Sprint 2 2026-07-12 → 2026-07-18
Discovery & Requirements Architecture & Planning
S3
Sprint 3 2026-07-19 → 2026-07-25
Architecture & Planning UX/UI & Technical Design
S4
Sprint 4 2026-07-26 → 2026-08-01
UX/UI & Technical Design Development
S5
Sprint 5 2026-08-02 → 2026-08-08
Development
S6
Sprint 6 2026-08-09 → 2026-08-15
Development
S7
Sprint 7 2026-08-16 → 2026-08-22
Development
S8
Sprint 8 2026-08-23 → 2026-08-29
Development
S9
Sprint 9 2026-08-30 → 2026-09-05
Development Integration & QA
S10
Sprint 10 2026-09-06 → 2026-09-12
Integration & QA
S11
Sprint 11 2026-09-13 → 2026-09-19
Integration & QA UAT
S12
Sprint 12 2026-09-20 → 2026-09-26
Deployment Hypercare